About

Project

NM 14 Study and Rehabilitation

View all projects

Project

These improvements and anticipated funding and construction timeframes are as follows:

  • Pavement Rehabilitation in three phases:
    • Phase 1: Milepost 0 to 2, Completed Fall 2018
    • Phase 2: Milepost 2 to 4, Funding programmed in 2018 and 2019, Anticipated Construction Spring/Summer 2019
    • Phase 3: Milepost 4 to 6, Spring 2020
  • Slope Stabilization for slope on east side on NM 14 between milepost 3.5 and 4.2. TBD 
  • Intersection Evaluation of NM 14 / NM 536 / Frost Rd intersection and development of alternatives for reconstruction. TBD

https://dot.state.nm.us/content/dam/nmdot/D3/NM14-Presentation.pdf

Project Sponsor: NMDOT

Comments or questions may be sent to the following addresses:

WSP
Attn: NM 14
6100 Uptown Blvd. NE, Suite 700
Albuquerque NM 87110
(505) 878-6554
Email: Paul.Steffin@wsp.com

NMDOT
7500 Pan American Freeway NE
Albuquerque, NM 87109
(505) 934-0354
Email: Leslie.Fortier@state.nm.us